Roles & Responsibilities :
This is a full-time position will be responsible in providing support to the team leaders and upper management.
General responsibilities
- Ensure 5S is maintained in the respective work area (Debinding, Sintering & Heat treatment)
- 5S check list should be filled at the start of every shift
- All parts must be clearly identified with the respective sintering cycle number / heat treatment cycle number
- Unidentified parts / fallen parts must be properly disposed in the FOD bin
- Move parts which are cleared by Quality from one process to the next as per the route card
Sintering
Load sintering fixture as per the planEnsure the parts loaded on the fixture can be combined in one cycle as per the recipe list available near each sintering furnaceEnsure parts are being staged on the sintering fixture are as per staging instructionIf no plan is available, take initiative to check with the team lead about the next planLoad the sintering fixture in the sintering furnace as per plan and start the cycleEnsure proper recipe is selected for the sintering cyclePrepare run sheets by ensuring correct quantities are being transferred and all the check points are verifiedDisplay run sheets on the sintering furnacePrint the route cards from doc-pro for each part loaded on the sintering fixtureSinter ID, date, quantity, process start date & shift, process end date & shift should be filled on the route cardUnloading of fixture after completion of cycleUnloading of parts from the fixture into bins and label each bin with part number, cycle number and quantity.Filing the run sheets in the filing cabinets after unloading the partsMoving the ceramics to the ceramic storage area to their respective locationsClean Sintering fixture using vacuum cleaner after unloading every cycleHeat Treatment
Load heat treatment fixture as per the planEnsure the parts loaded on the fixture can be combined in one cycle as per the recipe list available near the heat treatment planning boardEnsure parts are being staged on the heat treatment basket as per staging instructionIf no plan is available, take initiative to check with the team lead about the next planLoad recipes on the heat treatment computer as per the planPrepare run sheets by ensuring correct quantities are being transferred and all the check points are verifiedFile the old route card which has the information about the previous process carried and QC stamp in the filing cabinetsCeramic cleaning and Magazine preparation
Clean ceramics and prepare magazines for molding